Flood Recovery Campus Status Report
The Flood of 2016 damaged six schools and multiple school district facilities. The following information will be updated periodically in order to keep the public informed about our recovery.
FLOOD RECOVERY CAMPUS STATUS REPORT
Updated 10-15-19
Click here for Frequently Asked Questions | Click here for the a one-page flood recovery update
GALVEZ PRIMARY | GALVEZ MIDDLE | LAKE ELEMENTARY | ST. AMANT PRIMARY | ST. AMANT MIDDLE | ST. AMANT HIGH
GALVEZ PRIMARY
Temporary Buildings on Home Campus
- Galvez Primary Site Plan
- Structures: Administration Building, Library, Dining Hall, Classrooms (3 Pods of 10 Classrooms)
- Work Complete: Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Connection of Utilities, Delivery of Furniture, Relocation of Teacher Materials, Inspection and Permitting by All Public Agencies
- Move-In Date: Mar. 2, 2017
Permanent Repairs
- Work Complete: Flood Assessments, Architect Selection
- Work in Progress: Final Completion Imminent
- Target Completion Date: August 2018
DEMOBILIZATION OF TEMPORARY BUILDINGS
- Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
- Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways, and Associated Utilities
- Target Completion Date: November 2018
GALVEZ MIDDLE
Temporary Buildings on Home Campus
- Galvez Middle Site Plan
- Structures: Library, Dining Hall, Classrooms (3 Pods of 8 Classrooms plus 1 T-Building of 2 Classrooms) and Band Hall
- Work Complete: Administration Offices (Building not Impacted by Flood); Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen , Delivery of Furniture, Connection of Utilities, Inspection and Permitting
- Move-In Date: Mar. 13, 2017
Permanent Repairs
- Work Complete: Flood Assessments, Architect Selection
- Work in Progress: Final Completion Imminent
- Target Completion: August 2018
DEMOBILIZATION OF TEMPORARY BUILDINGS
- Structures: Library, Dining Hall, Classrooms (3 Pods of 8 Classrooms plus 1 T-Building of 2 Classrooms) and Band Hall
- Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways, and Associated Utilities
- Target Completion Date: September 2018
LAKE ELEMENTARY
Temporary Buildings on Home Campus
- Lake Elementary Site Plan
- Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
- Work Complete: Modular Buildings Delivered and Installed, Installation of Classroom Technology, Construction of Covered Walkways, Restoration of Flooded Kitchen, Connection of Utilities, Delivery of Furniture, Inspection and Permitting, Relocation of Teacher Materials
- Move-In Date: Mar. 6, 2017
Permanent Repairs
- Work Complete: Flood Assessments, Architect Selection, Design
- Work in Progress: Final Completion Imminent
- Target Completion Date: August 2018
DEMOBILIZATION OF TEMPORARY BUILDINGS
- Structures: Administration Building, Library, Dining Hall, Classrooms (4 Pods of 8 Classrooms and 2 Pods of 10 Classrooms) and Band Hall
- Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways, and Associated Utilities
- Target Completion Date: November 2018
ST. AMANT PRIMARY
Current School Locations
- PreK – 5th Grade Students at the Old RPCC Campus
Permanent Repairs
- Work Complete: Flood Assessments, Architect Selection, Design, Construction Bid
- Work in Progress: Complete
- Target Completion Date: Complete
ST. AMANT MIDDLE
Current School Location
- Home Campus
Temporary Buildings on Home Campus
- Structure: Band Hall
- Work Complete: Buildings Occupied and Not Impacted by Flood (Administration, Library, Main Classroom Buildings, Main Gym), Temporary Restoration of Kitchen, Delivery and Installation of Temporary Band Hall, Inspection and Permitting
- Work Pending: Complete
- Completion Date: Mar. 6, 2017
Permanent Repairs
- Work Complete: Flood Assessments, Architect Selection, Design, Construction Bid
- Work in Progress: Complete
- Target Completion Date: Complete
ST. AMANT HIGH
Temporary Buildings on Home Campus
- St. Amant High Site Plan
- Structures: Classrooms (6 Pods of 10 Classrooms and 5 T-buildings of 2 Classrooms) 2 Band Halls
- Work Complete: Freshman Academy (Includes Administration Offices, Classrooms, Cafeteria and Kitchen); Office Furniture Delivered; Modular Buildings Delivered and Installed, Construction of Covered Walkways, Installation of Classroom Technology, Connection of Utilities, Inspections and Permitting, Relocation of Teacher Materials, Installation and Permitting of Band Hall
- Move-In Date: Feb. 13, 2017
Permanent Repairs
- Work Complete: Flood Assessments, Architect Selection
- Work in Progress: Under Construction - On Schedule
- Target Completion Date: December 2018
DEMOBILIZATION OF TEMPORARY BUILDINGS
- Structures: Administration Building, Library, Dining Hall, Classrooms (3 Pods of 10 Classrooms)
- Work Complete: Removal of Modular Buildings, Classroom Technology, Covered Walkways, and Associated Utilities
- Work in Progress: In Design - On Schedule
- Target Completion Date: March 2019